Liquidated Damages Risk Checker in Florida Construction Contracts

Liquidated damages clauses set a fixed daily penalty for missed completion dates. Poorly negotiated LDs can wipe out an entire project margin in weeks — courts uphold them as long as they're not an unenforceable penalty.

Legal Risk · Florida

Enforced when reasonable; caps rare in private construction contracts.

Florida: enforced under Lefemine v. Baron, 573 So.2d 326 — must be reasonable pre-estimate, not a penalty

Potential Dollar Impact
$1,000 – $25,000 per day

Typical exposure per project when a LDs clause slips into a signed contract.

If you're the General Contractor

Include a written finding that damages would be difficult to prove — this insulates the clause.

If you're the Subcontractor

Florida courts will strike LDs as a penalty if they're grossly excessive relative to the project size.

Free Micro-Tool · 10-Second Scan

Drop your contract PDF — we'll flag LDs risk in seconds.

Vowpace's AI extracts liquidated damages language, redlines it against safer alternatives, and generates an audit-grade evidence report — free for your first scan.

Drop a contract PDF here

or click to browse · Max 8 MB

No credit card. Redactions run before AI ever sees your data.
Sample Redline · Florida

The clause we flag — and the one we help you write instead.

Risky boilerplate
Common LDs clause
“Contractor shall pay Owner the sum of Ten Thousand Dollars ($10,000) per calendar day for each day beyond the Substantial Completion Date, without regard to cause.”
Vowpace-recommended
Safer Florida-friendly rewrite
“Contractor shall pay Owner liquidated damages of Two Thousand Dollars ($2,000) per calendar day of unexcused delay beyond the Substantial Completion Date, subject to a cap of five percent (5%) of the Contract Sum. Excusable delays (force majeure, owner-caused, differing site conditions) shall extend the completion date on a day-for-day basis.”
Three things to watch during negotiation
  • 1Always negotiate an aggregate LD cap (typically 5–10% of Contract Sum).
  • 2Push for a mutual excusable-delay clause with a defined force majeure list.
  • 3Require Owner to prove actual damages remain difficult to estimate — otherwise LDs become an unenforceable penalty.
More Florida clause guides
Same clause in other states
Ready in 10 seconds

Scan your Florida contract for LDs traps — free.

Get an audit-grade evidence report showing exactly which clauses expose you and how to renegotiate them. No credit card.