Florida
Payment Shift

Pay-When-Paid / Pay-If-Paid Risk Checker in Florida Construction Contracts

'Pay-if-paid' shifts the risk of owner non-payment entirely onto the subcontractor. 'Pay-when-paid' merely delays timing. Confusing the two can cost you the entire subcontract value.

Legal Risk · Florida

Pay-if-paid enforceable IF clearly and unambiguously drafted as condition precedent.

Florida: DEC Elec., Inc. v. Raphael Constr. Corp., 558 So.2d 427 (1990)

Potential Dollar Impact
Full subcontract value

Typical exposure per project when a PWP / PIP clause slips into a signed contract.

If you're the General Contractor

Florida requires very explicit condition-precedent language. Ambiguity is construed against the drafter.

If you're the Subcontractor

In FL, courts strictly interpret pay-if-paid clauses against the GC. Any ambiguity means you get paid on a reasonable-time basis.

Free Micro-Tool · 10-Second Scan

Drop your contract PDF — we'll flag PWP / PIP risk in seconds.

Vowpace's AI extracts pay-when-paid / pay-if-paid language, redlines it against safer alternatives, and generates an audit-grade evidence report — free for your first scan.

Drop a contract PDF here

or click to browse · Max 8 MB

No credit card. Redactions run before AI ever sees your data.
Sample Redline · Florida

The clause we flag — and the one we help you write instead.

Risky boilerplate
Common PWP / PIP clause
“Contractor's receipt of payment from Owner is a condition precedent to Contractor's obligation to pay Subcontractor, and Subcontractor assumes the risk of Owner's non-payment.”
Vowpace-recommended
Safer Florida-friendly rewrite
“Contractor shall pay Subcontractor within seven (7) days of Contractor's receipt of the corresponding payment from Owner, provided that in no event shall payment be delayed more than sixty (60) days from Subcontractor's approved application for payment. This clause governs timing only and is not a condition precedent to payment.”
Three things to watch during negotiation
  • 1Look for the phrase 'condition precedent' — this is the pay-if-paid trigger.
  • 2Insist on a hard outside date (e.g., 60 or 90 days) regardless of Owner payment.
  • 3In many states, pay-if-paid clauses must be conspicuous and unambiguous to be enforceable.
More Florida clause guides
Same clause in other states
Ready in 10 seconds

Scan your Florida contract for PWP / PIP traps — free.

Get an audit-grade evidence report showing exactly which clauses expose you and how to renegotiate them. No credit card.

See Pro pricing

vowpace.com · Contract lifecycle for construction teams.

Legal Disclaimer

Vowpace AI is a milestone management and productivity tool. It does not provide legal advice, legal analysis, or binding legal services. Users are solely responsible for verifying and confirming AI-extracted milestones.