Retainage & Withholding Risk Checker in Florida Construction Contracts

Retainage is money withheld from every progress payment (typically 5–10%) until final completion. Excessive or slow-released retainage strangles subcontractor cash flow — many states now cap retainage by statute.

Legal Risk · Florida

Public: 5%. Private: no statutory cap, but 5–10% market standard.

Florida Statute §255.078 — 5% retainage cap on public projects; private negotiable

Potential Dollar Impact
5% – 15% of Contract Sum

Typical exposure per project when a Retainage clause slips into a signed contract.

If you're the General Contractor

Florida caps public-project retainage at 5%. Private contracts can go higher but 10% is a red flag.

If you're the Subcontractor

On Florida public jobs, retainage above 5% is capped by statute. On private, negotiate for 5% + early reduction.

Free Micro-Tool · 10-Second Scan

Drop your contract PDF — we'll flag Retainage risk in seconds.

Vowpace's AI extracts retainage & withholding language, redlines it against safer alternatives, and generates an audit-grade evidence report — free for your first scan.

Drop a contract PDF here

or click to browse · Max 8 MB

No credit card. Redactions run before AI ever sees your data.
Sample Redline · Florida

The clause we flag — and the one we help you write instead.

Risky boilerplate
Common Retainage clause
“Contractor may withhold ten percent (10%) of each progress payment as retainage, to be released in full only upon Contractor's receipt of final payment and closeout of all subcontracts on the Project.”
Vowpace-recommended
Safer Florida-friendly rewrite
“Contractor shall withhold five percent (5%) of each progress payment as retainage. Retainage shall be reduced to two and one-half percent (2.5%) upon fifty percent (50%) completion. Subcontractor's retainage shall be released within thirty (30) days of Subcontractor's substantial completion of its scope, independent of other subcontracts on the Project.”
Three things to watch during negotiation
  • 1Push for early retainage reduction at 50% completion.
  • 2Separate your retainage release from other subs — don't be held hostage to a slow-poke.
  • 3Verify state statutory retainage caps — public projects often have stricter limits.
More Florida clause guides
Same clause in other states
Ready in 10 seconds

Scan your Florida contract for Retainage traps — free.

Get an audit-grade evidence report showing exactly which clauses expose you and how to renegotiate them. No credit card.

See Pro pricing

vowpace.com · Contract lifecycle for construction teams.